1. 33/11 kv S/S is under construction-01 no.
2. Construction of 33 kv line- 11km
3. 11 kv line under construction-20 km
4. 11/0.4 kv line under construction-20km
5. 0.4 kv line under construction-10km
6. 11/0.4 kv distribution transformer under construction- 20 nos
7. Repair work of 33 kv line under process-35km
8. Repair work of 11 kv line under process-10km
9. Repair work of 0.4 kv line under process-15km
10. Up-gradation of distribution transformer.
Planning and Implementation: Cabinet Division, A2I, BCC, DoICT and BASIS