Achievements

Sl No

Subject

Start at 2009

At February 2018

Achievement

01

Installed capacity of grid sub-station

100 MVA

150 MVA

50 MVA (50%)

02

33/11 KV S/S

02

03

01 (50%)

03

Installed capacity of S/S

40 MVA

80 MVA

40 MVA (100%)

04

Power Transformer

04

08

04 (100%)

05

Distribution Tr

228

304

76 (33%)

06

33 KV Line

40 km

56 km

16 km (40%)

07

11 KV Line

140 km

220 km

80 km (57%)

08

Complain center

01

02

01 (100%)

09

No’s of consumers

35000

58000

23000 (65%)

10

System Loss

16.85%

9.85%

7.00% (-41.00%)

11

Monthly Bill

4 core

8 core

4 core (100%)

12

Load demand

22 mw

32 mw

10mw (45%)