Sl No |
Subject |
Start at 2009 |
At February 2018 |
Achievement |
01 |
Installed capacity of grid sub-station |
100 MVA |
150 MVA |
50 MVA (50%) |
02 |
33/11 KV S/S |
02 |
03 |
01 (50%) |
03 |
Installed capacity of S/S |
40 MVA |
80 MVA |
40 MVA (100%) |
04 |
Power Transformer |
04 |
08 |
04 (100%) |
05 |
Distribution Tr |
228 |
304 |
76 (33%) |
06 |
33 KV Line |
40 km |
56 km |
16 km (40%) |
07 |
11 KV Line |
140 km |
220 km |
80 km (57%) |
08 |
Complain center |
01 |
02 |
01 (100%) |
09 |
No’s of consumers |
35000 |
58000 |
23000 (65%) |
10 |
System Loss |
16.85% |
9.85% |
7.00% (-41.00%) |
11 |
Monthly Bill |
4 core |
8 core |
4 core (100%) |
12 |
Load demand |
22 mw |
32 mw |
10mw (45%) |
Planning and Implementation: Cabinet Division, A2I, BCC, DoICT and BASIS